...subways between Harvard square and Boston. These conferences have resulted in plans, satisfactory to both parties, which call for two two-track subways from Harvard square, one under Massachusetts avenue and Main street to the new Cambridge Bridge and the other under Cambridge street to the new Charles River Dam...
...Charles River Basin Commission last autumn submitted to the War Department its general construction plans for the Charles river dam. The contract has been awarded and work was begun last week. The dam will be erected a short distance below the Craigie or East Cambridge bridge, and the latter will be torn down and a temporary bridge constructed to take its traffic. The cost of the dam, which will not be completed for three years, will be about $2,500,000, or rather less than the original estimate. Unlimited appropriations have been voted by the state legislature and the work...
There will be two coffer-dams and a navigation lock 350 feet long, with a drawbridge and sluices. On top of the dam a roadway will be constructed to replace the Craigie bridge, and a parkway of seven acres will be laid out. The dam will turn the estuary of the Charles river into a fresh water basin, maintaining a level two feet lower than mean high water...
...dam will maintain a basin 8 miles long and will affect the level of the water as far as the dam at Watertown. There will be 17 1-2 miles of shore-line, nearly all of which will be devoted to park purposes, the land having been purchased by the Metropolitan Park Commission and the City of Cambridge. The level of the basin will be about 2 feet below the present mean high tide level...
...benefits of the basin will be realized much sooner than was anticipated by the petitioners who secured the legislative act authorizing the work. Part of the engineering scheme for the construction of the dam provides for a temporary shut-off which will establish the level of the basin at about the same level as the permanent structure. The terms of the contract call for the completion of this shut-off dam by August 1, 1907. Rowing men of the present Freshman class, therefore, will be able to enjoy, for a year at least, the advantages of the greater depth...