Edward Lashman, University director of external projects, said yesterday the changes are not fundmental because the purpose of the construction project, to provide power, has not changed...

Author: By George K. Sweetnam, | Title: Utility Firm Brings Suit To Block Power Project | 11/16/1977 | See Source »

...January 1976, after the BRA issued its approval of the original project plans, Boston Edison filed a suit claiming that the project did not constitute an urban renewal project for "public use and benefit...

Author: By George K. Sweetnam, | Title: Utility Firm Brings Suit To Block Power Project | 11/16/1977 | See Source »

...Boston Redevelopment Authority (BRA) originally approved the project two years ago, but inadequacies in the plan--in engineering and environment quality considerations--led to a set of plan modifications that the BRA approved October...

Author: By George K. Sweetnam, | Title: Utility Firm Brings Suit To Block Power Project | 11/16/1977 | See Source »

Boston Edison argues in its suit that the modifications in the plan were fundamental change, and that the BRA should have followed the more time-consuming path of considering the modified plans as a completely new project...

Author: By George K. Sweetnam, | Title: Utility Firm Brings Suit To Block Power Project | 11/16/1977 | See Source »

...examined the modified plans as representing a fundamental change in the power project, it might not have approved the project, it might not have approved the proved, John J. Murphy, public information director for Boston Edison, said yesterday...